The inspections works on Subsea MOHO Project and Subsea Aasta Hansteen Project
Kliknij na zdjęcie, aby powiększyć
At the end of September 2014 SEC inspectors complete the first part of the supervision works on Moho Subsea Project and Subsea Aasta Hansteen Project . Within our frame agreement our engineering staff supervises the implementation of the elements: constructions NL1001, NL1002, NL1003, NL1004, BL41, BL12, BLGLM, structures Anchor Top’ow BA12, BAGLM, BASDU, NAKKF2, NAFPU – Total weight of constructions is 900 tons. Constructions Anchor Top’ow HA, LU, SN - Total weight of elements is 300 tons. The inspection works for our Norwegian customer Aker Egersund take place in EPG Gdynia.